Concrete batching plant host discharge door can not be open

Concrete batching plant host discharge door can not be open

When the Concrete batching plant host discharge door can not be open, when the stirring was completed discharge lamp does not light.

Analyze the reasons may be: a foreign object or material between the discharge door and the sealing plate; inadequate gas system pressure, leak or damage the cylinder lubricator; wiring between the solenoid valve and the relay off, relay virtual connection or damaged; solenoid coil burning or spool seizure; time relay damage caused PLC without the normal input signal.

Processing concrete mixing station failure is: If a foreign body or material between the discharge door and the sealing plate, should clean the foreign body, the product material and rinse the discharge door; if insufficient pressure gas system, leak or damage the cylinder lubricator , you should check the lubricator, whether fittings, cylinders and other parts damaged; if the wiring between the solenoid valve and relay shedding relay virtual connection or damaged, you should check the relay contact output and wiring, replace if necessary; if the solenoid coil burn loss or spool jamming, replace the solenoid valve; if the time relay is damaged, should be replaced.